A project’s roadmap has been worked out to describe synthetically when and where activities will be deployed along the timeline. The simultaneous replacement of the power converters, the deployment of the demineralised water distribution and the renovation of the electrical switchboards in the BAs represent a considerable work that would heavily impact the NA operation if done during the beamtime, thus they are planned to take place during a LS. Some other activities can take opportunity of the End Of The Year Shutdowns ((E)YETS) to be deployed and not affecting the operation.