North Area Infrastructure

The surface in CERN’s North Area that is already renovated and going to renovated covers about 60 000 m2 above and below ground.

The underground structures connect the SPS proton beam with the experimental halls and also contain the targets, where the secondary and tertiary beams are produced. This whole complex covers 16620 m2.

Underground Structures

NameTypeDescriptionSurface (m2)

TT20

tunnelExtracted proton beam from SPS. Only the last part of it is included in the NA consolidation program.1869
TDC2cavernExtracted proton beam and splitter switchyard.1908
TCC2cavernTarget zone and start of secondary (particle) beams.2080
TT81tunnelConnects TCC2 to EHN1 surface experimental hall, houses the H2 and H4 secondary beam lines.1241
TT82tunnelConnects TCC2 to EHN1 surface experimental hall, houses the H6 and H8 secondary beam lines.1241
TT83tunnelStarts from TCC2, houses the M2, P0 and P61 beam lines1809
TDC8cavernJunction cavern switch of M2 and P0 beam lines.567
TT85tunnelStarts from TDC8, houses the P0 beam line.454
TDC85cavernJunction cavern, houses the P0 beam line. It used to contain the switch to a second primary or ion beam line to the ECN3 cavern.861
TCC8cavernTarget cavern for the T10 target. Contains the upstream part of the K12 beam line to ECN3 underground experimental cavern.1700
TT84tunnelConnects the TDC8 to EHN2 experimental hall. Houses the M2 beam line.2386
TA801galleryTechnical gallery connecting TCC2 to BA80282
TA802galleryTechnical gallery connecting TCC2 to BA80104
913tunnelAccess point59
914tunnelAccess point59
Total16620 m2

Experimental Halls

NameTypeDescriptionSurface (m2)
EHN1surfaceExperimental Hall 1 (b.887) housing the H2, H4, H6, and H8 beam lines.25928
EHN2surfaceExperimental Hall 2 (b.888) housing the M2 beam line.3267
ECN3cavernUnderground Experimental Cavern 3 (900) housing the K12 beam line1887
Total31082 m2

Surface Service Buildings

NameTypeDescriptionSurface (m2)
BA80b.889Access point for TCC2/TDC2 zones and location of infrastructure services (cooling, ventilation), power supplies and beam instrumentation.3103
BA81b.890Infrastructure services (cooling, ventilation) underground tunnels downstream TCC2 and experimental halls, power supplies for secondary beams.3596
BB81b.895Infrastructure services (cooling, cryogenics) for underground tunnels and experimental halls. Gas system distribution1949
BG810b.907Gas building for experimental halls EHN1.400
BA82b.891Infrastructure services (cooling, ventilation) underground tunnels downstream EHN1, power supplies for M2 and P0/K12 secondary beams.1074
BY82b.883Infrastructure services for cooling and ventilation for EHN2.243
BX82b.906Auxiliary building for beam instrumentation and monitoring.33
BG82b.908Gas building for ECN346
BG83b.920Gas building for EHN248
BX83b.918Counting rooms for ECN3 experimental cavern.847
PA852b.911Access point for ECN3 underground cavern396
PP851b.912Access point for TCC8 target cavern165
BG811b.909Gas building for EHN1176
BX80b.902Auxiliary building for beam instrumentation for EHN168
Total12044 m2